2022/12/29 3rd and McCracken

Image
Forms are set waiting for rebar before pouring floor Contractor setting silt sock to protect streams from soil erosion 

2022/12/27 3rd and McCracken

Image
Starting to excavate West McCracken Rd for the new box culvert Continue to excavate for the McCracken box culvert Finished the day with about 75% of the McCracken Rd box culvert excavated

2022/12/19 3rd and McCracken

Image
            Removing trees for the new walking path North of Finley Chapel next to West McCracken Continue to clear debris where new walking trail will be installed  Clearing ROW at the corner of 3rd and Jackson  Finished with tree removal just North of the park entrance 

2022/12/28 3rd and McCracken

Image
Excavation of box culvert completed, placing rock for compaction and leveling