2023/1/31 3rd and McCracken

Image
Contractor did not show due to extreme weather 

2023/1/30 3rd and McCracken

Image
Contractor did not show due to extreme weather 

2023/1/23 3rd and McCracken

Image
Tree removal for water line installation  Continue to excavate for the force main 

2023/1/26 3rd and McCracken

Image
Contractor did not show due to cold weather and snow on the ground

2023/1/25 3rd and McCracken

Image
Contractor no show due to snow storm 

2023/1/24 3rd and McCracken

Image
Finish placing force main by North end of lift station  Contractor is heading south on 3rd street with water line

2023/1/19 3rd and McCracken

Image
Backfilling box culvert on McCracken Breaking asphalt on both sides of box on McCracken Continue with excavation for force main Continue with breaking of the asphalt

2023/1/18 3rd and McCracken

Image
Contractor showed up this morning to cover waterlines  Waterline connected and buried for the day

2023/1/17 3rd and McCracken

Image
Grouting box culvert on McCracken  Continue with water line on 3rd street 

2023/1/16 3rd and McCracken

Image
Continue with water line up 3rd street  Concrete top poured on the McCracken box Continue with water line on 3rd street 

2023/1/13 3rd and McCracken

Image
Excavating around lift station for new force main and trail Top of McCracken box rebar complete ready for Mondays pour weather permitting. Continue with force main and waterline  Finish day with covering water and force main heading North