Arrived on site at 4 pm, contractor was applying base to the roadway and sidewalk, saw cutting curb. Contractor has built Crane pad to start on Bridge rehab.
Arrived onsite at 8:30 am to test concrete for Curb, Truck arrived at 9:09 am. Aaron tested concrete; Air 3.4% had to add air. Retested air 4.5%, Slump 1/2", Temp 64°. They started laying curb.