2023/5/24 3rd and McCracken

2023/5/23 3rd and McCracken

Image
 Placing black dirt throughout project for seeding Contractor grading for walking trail Placed Pyramat 25 on 3rd street slope Continue to cut intermediate bent  Adding final coat on span 2 of the bridge

2023/5/22 3rd and McCracken

Image
Coring and cutting to remove part of intermediate bent  Continue with painting span 2 of bridge 

2023/5/19 3rd and McCracken

Image
Continue with painting span 2 of bridge  Grass is starting to grow throughout project  Sidewalk completed at 3rd and Jackson

3rd & McCracken 5-17-2023

Image
Arrived at 8:50 to test concrete for sidewalk along wall, tested concrete; Slump 4-1/4”, Air 4.25%, retested and came up to 4.9%, Temp 74. Made a set of cylinders  Crew was starting on painting bridge 

2023/5/16 3rd and McCracken

Image
Platform set to remove top half of intermediate bent Continue with painting on span two

2023-5-15 3rd & McCracken

Image
Arrived at 12:50, contractor was back filling wall at 3rd and Jackson. Sun was cleaning bridge getting ready to paint. One guy was working on intermiate bent.

2023/5/12 3rd and McCracken

Image
Inspection of bridge repairs  Continue with pressure washing on east truss 

2023-5-11 3rd & McCracken

Image
Arrived at 10:50 and no work being performed due to rain.

2023/5/10 3rd and McCracken

Image
Starting to pour curb and gutter at the corner of 3rd and Jackson  Black dirt has been placed, seeded and straw. Continue to work on bridge repairs Pressure washing to continue