2023/3/20 3rd and McCracken Get link Facebook X Pinterest Email Other Apps March 20, 2023 Arrived onsite at 11:30, Contractor was ready to pour Drive at Chapel.Adrian tested concrete, Air we a 4%, Slump 4-1/2", Temp 60°Started PourFinished Pour, Made four Cylinders for early break.A lot going on today other than pour, base compaction, utility work and clean up Get link Facebook X Pinterest Email Other Apps Comments
2023/8/7 3rd and McCracken August 07, 2023 Pouring curb for side walk on the South side of bridge Removing riprap from stream Read more